Logo header
About Us
Projects
Supplies / Services provided to Worksites
Contact Us
HOME >> Projects >> In Progress
in progress


CAIRO METRO – EGYPT (LINE 3, PHASE1)

Place: Line No. 3 extends from the north west of the Greater Cairo at Imbaba to the north-east at Heliopolis and will eventually also serve the Cairo International Airport.

Project: The total length of the line is approximately 30 kilometres (19 miles) most of which is in bored tunnel and will be implemented in four phases.

Client: National Authority for Tunnels (NAT)

Joint Venture:
  • Composition 28,5 % VINCI
  • 27,5 % ArabCo
  • 26,0 % BYTP
  • 18,0 % ORASCOM

Detail of the Work:
The design of phase 1 is taking into consideration the safe crossing of two major underground structures; namely, the line 2 bored tunnel at Attaba and the wastewater spine tunnel north of Attaba. It is also planned that some of the underground stations will be extensively used as commercial centres. These stations will be constructed by the cut-and-cover method and the rolling stock will be fed by power through a third rail.

PRINCIPAL QUANTITIES:
Phase 1 will be 4.3 km long including:
  • 5 underground stations through nearly 4.2 km of tunnel, dig with TBM diameter 9.60 meters.
  • 22,000 Tons of steel rebars.
  • 30,000 Tons of structural steel.
  • More than 250,000 cm of concrete.

ISTRIAN MOTORWAY CROATIA (PHASE 2A)

Place: The construction of a full profile motorway is planned in phases, so that the entire work of doubling the Istrian motorway network is finished in the shortest time possible.

Project: Phase 2 (the construction of a double carriageway) Phase 2A works comprise the construction of sections for which the existing location (zoning) permits can be used, as well as the existing environmental impact studies.

Client: BINA ISTRA d.d

Phase 2A:
  • Umag – Kanfanar, except the Limska Draga Viaduct and the Mirna Bridge (49.2 km)
  • Kanfanar- Pula, including the new interchange of Vodnjan North (27.6 km)
  • Kanfanar-Rogovici (18 km)

The Istrian Motorway Phase 2 has been awarded to BOUYGUES TRAVAUX PUBLICS in September 2008. Works have started last October and the whole project is to be completed in March 2012.

It consists in the design and construction of a 100 Km tolled section of 2x1 lanes in Istria, Croatia, by enlarging the existing motorway constructed by Bouygues between 1998 and 2006. The project includes 5.5 million cubic meters of earth working, 80,000 cubic meters of concrete as well as 17 toll plaza stations with equipments and installations.

MOUNT ROSSER BYPASS, JAMAICA

Place: The road, a four-lane dual carriageway, will begin at the Bog Walk/Linstead bypass and bypass the town of Ewarton, Mount Rosser and Mount Diablo and continue through to Claremont just outside of Moneague.

Project: Covers a range of aspects from land acquisition, road construction, building of a toll plaza and the installation of utilities. The project includes 13 structures including major river crossing as well as a toll plaza with equipments and instrumentations.

Client: The project will be undertaken by TransJamaican Highway/Bouygues, which were the developers of Highway 2000. The work is scheduled to be completed in 30 months.

“The contract was awarded to Bouygues to start work on the Mount Rosser section, on the basis of Bouygues having enough knowledge of the terrain based on work they were doing with the bauxite companies," Henry told the Observer after the launch.

Assembling Contract: The Mount Rosser Bypass project, which is a part of the North-South link of Highway 2000, was originally scheduled to cost US$108.5 million and be completed by January 2010, but this has been revised to US$135.5 million and a completion date of January 2011.



NEW TYNE CROSSING, NEWCASTLE, U.K.

Place: Newcastle - United Kingdom

Project: The New Tyne Crossing is the project to design and build a second vehicle tunnel under the River Tyne, refurbish the existing vehicle tunnel and to operate and to maintain all the tunnels under the river until 2037. It is one of the biggest transport infrastructure projects currently active in Great Britain.

Client: On April 12 2007, the Tyne and Wear Passenger Transport Authority (TWPTA) appointed a consortium of companies led by Bouygues Travaux Publics, to deliver the New Tyne Crossing.

Assembling Contract: The New Tyne Crossing represents a £260 million capital investment in road infrastructure in Tyne & Wear.


Detail of the Work:
The new tunnel will run under the River Tyne between East Howdon and Jarrow, and will complete the dualling of the A19 from its junction with the A1 in South East Northumberland to North Yorkshire.


PRINCIPAL QUANTITIES:
The new tunnel design and construction of a new vehicle tunnel consists of:
  • 320 m : North cut & cover
  • 22,000 Tons of steel rebars.
  • 30,000 Tons of structural steel.
  • More than 250,000 cm of concrete.

NEW SAFE CONFINEMENT OF CHERNOBYL - UKRAINE

Place: Chernobyl - Ukraine

Project: The New Safe Confinement will be the replacement for the aging Sarcophagus currently covering the remains of Reactor 4 at the Chernobyl Plant. The Interim Storage Facility-2 will be used to deal with spent fuel from Chernobyl reactors 1-3. Contractors are currently working on design and technical details for both projects. Final designs are scheduled to be submitted to Ukrainian regulators in spring 2009.

Client: The commercial proposal of Novarka of Vinci Construction Grands Projets and BOUYGUES (both France) amounts to EUR 271.1 million

Detail of the Work: Ukraine's Ministry of Emergency Measures announced on January 24, 2008 that construction of the New Safe Confinement structure at the Chernobyl Atomic Energy Station will begin in earnest this spring. Physical work for clearing the area has began in September 2008, with the digging of NSC foundation areas to start in November. All work under this contract is expected to be complete by the end of 2009.

Principal Quantities :
Confinement fast facts*
  • Width: 257m (840ft)
  • Height : 105m (345ft)
  • Length : 150m (490ft)
  • Weight : approx. 20,000 tonnes
  • Construction time : 48-52 months
  • Life time : 100 years min.
* based on concept design specifications.



GAUTRAIN RAPID RAIL LINK PROJECT

(Construction is scheduled for completion in 2010)


Place:Johannesburg – Pretoria, South Africa

Project:The commissioning of this new rail link stretching over 80 km and linking Johannesburg, Pretoria and Johannesburg international airport should coincide with the 2010 Football World Cup. The project provides for the implementation of a high-speed train system.

Client:Provincial Government of Gauteng, South Africa

Detail of the Work:
The scope of this PPP (public private partnership) contract is the design, construction, operation and maintenance of this network as well as its financing. The concession period is of 19 years-and-a-half, out of which 4 and a half for the construction and 15 years of operation. The civil works will last four and a half year. They include the construction of:
  • 10 stations (3 of which underground)
  • 15 Km of tunnel sections
  • 9 Km of Viaduc and bridges
  • And 10 millions m3 of earthworks

CASTLE PEAK CABLE TUNNEL - HONG KONG

(Construction is scheduled for completion in March 2009)

Place: The tunnel starts at a tunnel portal located at CLP Castle Peak Power Station and passes beneath a mountainous region, finishing at a shaft near a town centre at Tuen Mun near Hong Kong

Project: Tunnel of 4,500 Meters length with a Diameter of 4.5 meters.

Client: CLP Power Hong Kong Limited (CLP Power)

Detail of the Work:
The tunnel which will be excavated using a rotary digger shield has hard soil and will ensure the passing of high tension cables from Castle Peak Power station to Tuen Mun. Construction works commenced in December 2005.

TANGIER PORT RO-RO- MOROCCO

(Construction is scheduled for completion in 2009)

Place: Tangier

Project: The on-going Tangier-Mediterranean port project will allow Morocco to improve its competitiveness, thanks to well connected infrastructure. It is hoped to attract investment and create jobs. The Tangier Mediterranean Special Agency [TMSA] stressed that the port, with a capacity of 3.5 million containers, 500,000 trucks and five million passengers, will serve as a platform linking Asia, America, Europe and Africa and a hub for international oil offshore traffic.

Client: TMSA (Agence Speciale Tanger Mediteranee)

Detail of the Work:
  • 2 Main Sea Walls of 1,230 meters each
  • 8 Ro-Ro Berths
  • Logistic Platform: 4ha
  • Draught up to 18 mln
  • Concrete prefabricated caissons: 23 Units of 7,900 Tons each
  • Concrete: 150,000 m3
  • Steel: 15,000 Tons
  • 860 Workers at Peak Time

FLAMANVILLE 3 EDF-EPR - FRANCE

(Construction is scheduled to start generating electricity in 2012)

Place: site located in the Manche Region

Project: A new nuclear power plant with a capacity of 1,650 MW. This power plant will be built with the European pressurised-water technology used for the EPR (European pressurised reactor). This project fully follows EDF's missions: generating, transmitting and selling electricity for all its customers and guaranteeing a clean, safe and competitive electricity.

Client: EDF

Assembling Contract: 3.3 billion Euro

Detail of the Work:
Eight years are necessary to be able to produce electricity: 5 years to finalize construction and 3 additional years for administrative procedures, before construction can begin. EDF goes ahead today in the construction of the first of what may become a possible series.

Safety and Technical Details:
The reactor is composed of 4 redundant safety trains, each within a separate building, to guarantee the safety of the operations, whatever happens. A shell of reinforced concrete protects the more sensitive buildings of Flamanville 3, which is a protection against external hazards. A core melt recovery device ("core catcher") has been installed in order to limit consequences of a hypothetical severe accident.



SHANGHAI CHANGJIANG RIVER CROSSING PROJECT

Place: Yangtze Delta - Shanghai

Project:
Total length: 25.5kmLanes: 2 x 3 lanesSpeed: 80km/h
Total investment: 12.3 bnYuan

Client: Shanghai Changjiang Tunnel & Bridge Development Co

Detail of the Work:
Located on the Yangtze estuary, the tunnel will link Shanghai’s Pudong district with Changxing Island, thus reducing by a factor of five the time that it currently takes to reach the island, popular with local residents in search of nature.A twin-tube, 8 km tunnel carrying three lanes in each direction, the ChongMing tunnel will form part of the longest river crossing road link in the world (25,5 km). And the 15.43 m width of the tunnel boring machine being used on the contract constitutes a world record in itself!

2 tunnels, 8 cross passages, internal structure:
East Tunnel: 7471.65m, with 6872.3m under river.
West Tunnel: 7469.36m, with 6854.91m under river.maxim slope: 2.9%, R4000m.
2 TBM Units (Tunnel boring machines) manufactured by Herrenknecht
Diameter: 15,430 mm
Design length: 134 meters

TOULON TUNNEL - FRANCE

(Construction is scheduled for completion in 2011)

Place: Toulon, Var (83), Provence-Aples, CÔTE D’AZUR - France

Project: A tunnel dug from a section of 120 m² two clear-cut trenches of access of 200 meters each

Client: Setec TPI & Terrasol

Principal Quantities :
  • 1,818 meters of tunnel,
  • 2 * 200 meters of clear cut trenches
  • 10 branches of communication with the existing tunnel, 56 months of work of which 44 months of effective duration (the last year will be used for the implementation of the final equipment),
  • Total of Work = 150 million Euros,

DTPT PROJECTS

Place: West Africa, Eastern Europe, France

Project: In 2005, DTP Terrassement saw sustained business in Cameroon, where it is building the longest road currently under construction in Africa (260 km). DTP Terrassement is also back in Burkina Faso, Congo and Equatorial Guinea where it is building two roads

Detail of the Work:
DTP Terrassement intends to press ahead with development in PPPs and concessions while continuing to diversify its business areas in France. Outside France, it is continuing to grow in Eastern Europe, with a profit centre set up in Poland, and in Africa, particularly in open cast mining. It is the first European company to have obtained ILO-OSH 2001 certification (occupational safety and health management).


CYPRUS & PAFOS INTERNATIONAL AIRPORTS

(Construction is scheduled for completion in 2013)

Place: Larnaca and Pafos

Project: An upgrade of Larnaca and Paphos airports has started and represents Cyprus's first Build-Operate-Transfer (BOT) project.

Detail of the Work:
Hermes is to build new passenger terminals and extend the runways at both airports under a 25-year concession. Larnaca’s first phase (due for completion in 2008) will serve 7.5m passengers a year.The arrivals hall was expanded in February 2006 adding two luggage belts bringing the total up to six, a smoking area, and a larger lounge. This was done as a 'stopgap' measure to better enable the airport to handle passengers until a new terminal is completed on a nearby site. A second phase, due to be completed in 2013, provides for the expansion of the terminal to cater for 9m passengers a year, and for a 500m runway extension. The design for the new 98,000 m2 Larnaca terminal includes 16 boarding bridges and is intended to reflect the proportions of a medieval aqueduct located in the city.